Activity Fields
About Field Names
Activity Fields names used in BimSens configuration are the names exposed by the Web Services, they differ from the standard name of the P6 user interface. Most Fields have an equivalent mapped below but some Web Services name are not visible in P6 and some P6 names are not (yet) available in BimSens and have no mapping.
Activity Codes and User Defined Fields are not listed below since they have the same names.
Mapping of Web Services Names and P6 Names of Activity Fields
(Mapping that have not been confirmed have a question mark)
Category |
P6 Common Name |
Name on Web Services |
Sure Map? |
Costs |
Actual Expense Cost |
ActualExpenseCost |
|
Actual Labor Cost |
ActualLaborCost |
|
|
Actual Material Cost |
ActualMaterialCost |
|
|
Actual Nonlabor Cost |
ActualNonLaborCost |
|
|
Actual This Period Labor Cost |
ActualThisPeriodLaborCost |
|
|
Actual This Period Material Cost |
ActualThisPeriodMaterialCost |
|
|
Actual This Period Nonlabor Cost |
ActualThisPeriodNonLaborCost |
|
|
Actual Total Cost |
ActualTotalCost |
|
|
At Completion Expense Cost |
AtCompletionExpenseCost |
|
|
At Completion Labor Cost |
AtCompletionLaborCost |
|
|
At Completion Material Cost |
AtCompletionMaterialCost |
|
|
At Completion Nonlabor Cost |
AtCompletionNonLaborCost |
|
|
At Completion Total Cost |
AtCompletionTotalCost |
|
|
|
Baseline1PlannedExpenseCost |
|
|
|
Baseline1PlannedLaborCost |
|
|
|
Baseline1PlannedMaterialCost |
|
|
|
Baseline1PlannedNonLaborCost |
|
|
|
Baseline1PlannedTotalCost |
|
|
|
BaselinePlannedExpenseCost |
|
|
|
BaselinePlannedLaborCost |
|
|
|
BaselinePlannedMaterialCost |
|
|
|
BaselinePlannedNonLaborCost |
|
|
|
BaselinePlannedTotalCost |
|
|
Variance - BL1 Expense Cost |
ExpenseCost1Variance |
? |
|
Variance - BL Project Expense Cost |
ExpenseCostVariance |
? |
|
Variance - BL1 Labor Cost |
LaborCost1Variance |
? |
|
Variance - BL Project Labor Cost |
LaborCostVariance |
? |
|
Variance - BL1 Material Cost |
MaterialCost1Variance |
? |
|
Variance - BL Project Material Cost |
MaterialCostVariance |
? |
|
Variance - BL1 Nonlabor Cost |
NonLaborCost1Variance |
? |
|
Variance - BL Project Nonlabor Cost |
NonLaborCostVariance |
? |
|
|
PlannedExpenseCost |
|
|
|
PlannedLaborCost |
|
|
|
PlannedMaterialCost |
|
|
|
PlannedNonLaborCost |
|
|
|
PlannedTotalCost |
|
|
Remaining Expense Cost |
RemainingExpenseCost |
|
|
Remaining Labor Cost |
RemainingLaborCost |
|
|
Remaining Material Cost |
RemainingMaterialCost |
|
|
Remaining Nonlabor Cost |
RemainingNonLaborCost |
|
|
Remaining Total Cost |
RemainingTotalCost |
|
|
Variance - BL1 Total Cost |
TotalCost1Variance |
? |
|
Variance - BL Project Total Cost |
TotalCostVariance |
? |
|
Dates |
Actual Finish |
ActualFinishDate |
|
Actual Start |
ActualStartDate |
|
|
BL1 Finish |
Baseline1FinishDate |
|
|
BL1 Start |
Baseline1StartDate |
|
|
BL Project Finish |
BaselineFinishDate |
|
|
BL Project Start |
BaselineStartDate |
|
|
|
DataDate |
|
|
Early Finish |
EarlyFinishDate |
|
|
Early Start |
EarlyStartDate |
|
|
Expected Finish |
ExpectedFinishDate |
|
|
External Early Start |
ExternalEarlyStartDate |
|
|
External Late Finish |
ExternalLateFinishDate |
|
|
Finish |
FinishDate |
|
|
Late Finish |
LateFinishDate |
|
|
Late Start |
LateStartDate |
|
|
Planned Finish |
PlannedFinishDate |
|
|
Planned Start |
PlannedStartDate |
|
|
Primary Constraint Date |
PrimaryConstraintDate |
|
|
Remaining Early Finish |
RemainingEarlyFinishDate |
|
|
Remaining Early Start |
RemainingEarlyStartDate |
|
|
Remaining Late Finish |
RemainingLateFinishDate |
|
|
Remaining Late Start |
RemainingLateStartDate |
|
|
Resume Date |
ResumeDate |
|
|
|
ReviewFinishDate |
|
|
Secondary Constraint Date |
SecondaryConstraintDate |
|
|
Start |
StartDate |
|
|
Suspend Date |
SuspendDate |
|
|
Durations |
Actual Duration |
ActualDuration |
|
At Completion Duration |
AtCompletionDuration |
|
|
BL1 Duration |
Baseline1Duration |
|
|
|
Baseline1PlannedDuration |
|
|
BL Project Duration |
BaselineDuration |
|
|
|
BaselinePlannedDuration |
|
|
Variance - BL1 Duration |
Duration1Variance |
? |
|
Variance - BL Project Duration |
DurationVariance |
? |
|
Variance - BL1 Finish Date |
FinishDate1Variance |
? |
|
Variance - BL Project Finish Date |
FinishDateVariance |
? |
|
Free Float |
FreeFloat |
|
|
|
PlannedDuration |
|
|
Remaining Duration |
RemainingDuration |
|
|
Remaining Float |
RemainingFloat |
|
|
Variance - BL1 Start Date |
StartDate1Variance |
? |
|
Variance - BL Project Start Date |
StartDateVariance |
? |
|
Total Float |
TotalFloat |
|
|
Earned Value |
Accounting Variance |
AccountingVariance |
|
Accounting Variance - Labor Units |
AccountingVarianceLaborUnits |
|
|
Variance At Completion - Labor Units |
AtCompletionLaborUnitsVariance |
|
|
Variance At Completion |
AtCompletionVariance |
|
|
Budget At Completion |
BudgetAtCompletion |
|
|
Cost Performance Index |
CostPerformanceIndex |
|
|
Cost Performance Index - Labor Units |
CostPerformanceIndexLaborUnits |
|
|
Cost Variance |
CostVariance |
|
|
Cost Variance Index |
CostVarianceIndex |
|
|
Cost Variance Index - Labor Units |
CostVarianceIndexLaborUnits |
|
|
Cost Variance - Labor Units |
CostVarianceLaborUnits |
|
|
Earned Value Cost |
EarnedValueCost |
|
|
Earned Value Labor Units |
EarnedValueLaborUnits |
|
|
Estimate At Completion Cost |
EstimateAtCompletionCost |
|
|
Estimate At Completion - Labor Units |
EstimateAtCompletionLaborUnits |
|
|
Estimate To Complete |
EstimateToComplete |
|
|
Estimate To Complete Labor Units |
EstimateToCompleteLaborUnits |
|
|
Planned Value Cost |
PlannedValueCost |
|
|
Planned Value Labor Units |
PlannedValueLaborUnits |
|
|
Schedule Performance Index |
SchedulePerformanceIndex |
|
|
Schedule Performance Index - Labor Units |
SchedulePerformanceIndexLaborUnits |
|
|
Schedule Variance |
ScheduleVariance |
|
|
Schedule Variance Index |
ScheduleVarianceIndex |
|
|
Schedule Variance Index - Labor Units |
ScheduleVarianceIndexLaborUnits |
|
|
Schedule Variance - Labor Units |
ScheduleVarianceLaborUnits |
|
|
To Complete Performance Index |
ToCompletePerformanceIndex |
|
|
Feedback |
Feedback from Resources |
Feedback |
? |
New Feedback |
IsNewFeedback |
|
|
Notes to Resources |
NotesToResources |
|
|
General |
Auto Compute Actuals |
AutoComputeActuals |
|
Calendar |
CalendarName |
? |
|
|
CalendarObjectId |
|
|
Added Date |
CreateDate |
|
|
Added By |
CreateUser |
|
|
Duration Type |
DurationType |
|
|
|
GUID |
|
|
|
HasFutureBucketData |
|
|
Activity ID |
Id |
|
|
|
IsBaseline |
|
|
Critical |
IsCritical |
|
|
Longest Path |
IsLongestPath |
|
|
|
IsTemplate |
|
|
Last Modified Date |
LastUpdateDate |
|
|
Last Modified By |
LastUpdateUser |
|
|
|
LevelingPriority |
|
|
Activity Name |
Name |
|
|
Primary Constraint |
PrimaryConstraintType |
? |
|
|
PrimaryResourceId |
|
|
Primary Resource |
PrimaryResourceName |
|
|
|
PrimaryResourceObjectId |
|
|
Project ID |
ProjectId |
|
|
Project Name |
ProjectName |
|
|
|
ProjectObjectId |
|
|
|
ReviewStatus |
|
|
Secondary Constraint |
SecondaryConstraintType |
? |
|
Activity Status |
Status |
? |
|
Activity Type |
Type |
? |
|
WBS |
WBSCode |
? |
|
|
WBSName |
|
|
|
WBSObjectId |
|
|
|
ObjectId |
|
|
Multiple Float Paths |
Float Path |
FloatPath |
|
Float Path Order |
FloatPathOrder |
|
|
Percent Completes |
Cost % Complete |
CostPercentComplete |
|
Cost % of Budget |
CostPercentOfPlanned |
? |
|
Duration % Complete |
DurationPercentComplete |
|
|
Duration % of Original |
DurationPercentOfPlanned |
? |
|
Expense Cost % Complete |
ExpenseCostPercentComplete |
|
|
Labor Cost % Complete |
LaborCostPercentComplete |
|
|
Labor Units % Complete |
LaborUnitsPercentComplete |
|
|
Material Cost % Complete |
MaterialCostPercentComplete |
|
|
Nonlabor Cost % Complete |
NonLaborCostPercentComplete |
|
|
Nonlabor Units % Complete |
NonLaborUnitsPercentComplete |
|
|
Activity % Complete |
PercentComplete |
|
|
Percent Complete Type |
PercentCompleteType |
|
|
Performance % Complete |
PerformancePercentComplete |
|
|
Physical % Complete |
PhysicalPercentComplete |
|
|
Schedule % Complete |
SchedulePercentComplete |
|
|
Units % Complete |
UnitsPercentComplete |
|
|
Units |
Actual Labor Units |
ActualLaborUnits |
|
Actual Nonlabor Units |
ActualNonLaborUnits |
|
|
Actual This Period Labor Units |
ActualThisPeriodLaborUnits |
|
|
Actual This Period Nonlabor Units |
ActualThisPeriodNonLaborUnits |
|
|
|
ActualTotalUnits |
|
|
At Completion Labor Units |
AtCompletionLaborUnits |
|
|
At Completion Nonlabor Units |
AtCompletionNonLaborUnits |
|
|
|
AtCompletionTotalUnits |
|
|
|
Baseline1PlannedLaborUnits |
|
|
|
Baseline1PlannedNonLaborUnits |
|
|
|
BaselinePlannedLaborUnits |
|
|
|
BaselinePlannedNonLaborUnits |
|
|
Variance - BL1 Labor Units |
LaborUnits1Variance |
? |
|
Variance - BL Project Labor Units |
LaborUnitsVariance |
? |
|
Variance - BL1 Nonlabor Units |
NonLaborUnits1Variance |
? |
|
Variance - BL Project Nonlabor Units |
NonLaborUnitsVariance |
? |
|
|
PlannedLaborUnits |
|
|
|
PlannedNonLaborUnits |
|
|
|
PlannedTotalUnits |
|
|
Remaining Labor Units |
RemainingLaborUnits |
|
|
Remaining Nonlabor Units |
RemainingNonLaborUnits |
|
|
|
RemainingTotalUnits |
|